I-85 SSI Traffic Alert: Multiple Road Closures and Lane Restrictions
Construction is advancing successfully across the I-85 Sanitary Sewer Improvement Project. The following Two Week Look Ahead covers Construction Packages 1 and 2 from August 31st through September 11th, 2026. Under Construction Package 1, JF Wilkerson crews plan to dechlorinate the new 8-inch waterline and collect a bacteriological sample before proceeding with restoration work. Crews will also advance the 20-inch force main leaving Joe Peed. Upcoming work is expected to incl
2 hours ago


11th Street Closure Begins August 31st
Pipeline construction associated with the I-85 Sanitary Sewer Improvement Project will begin at 8:00 a.m. on Monday, August 31, 2026, along 11th Street between West B Street and West C Street. Work is expected to continue for approximately four to six weeks, with access limited to local traffic during active construction.
5 days ago


I-85 SSI Project Two Week Look Ahead
The I-85 Sanitary Sewer Improvement Project continues to advance across several active work areas as crews move forward with pipeline installation, sewer testing and restoration, and microtunneling operations.
Aug 21


I-85 SSI Project - Central Avenue Re-opens
The Central Avenue road closure is scheduled to end by close of business today, ahead of the original estimated completion date of August 10th, 2026.
Jul 30


Rain Impacts I-85 SSI Project Construction Activity
Rain and saturated site conditions have affected construction activity across the I-85 Sanitary Sewer Improvement Project. Crews initially remained on standby while evaluating whether work could safely resume; however, pipe-laying and other active construction operations have since been called off for the remainder of the day.
Jul 23


Joe Peed Road Closure and Pipeline Installation
Access along East Middleton Road will be maintained. Next week, crews will cross Joe Peed Road with the 24” gravity sewer, 8” waterline, and proposed 24” force main. Joe Peed Road will be closed between S. Durham Avenue and WB Clark Road, July 27th through July 30th, with detours in place during closure.
Jul 21


I-85 SSI Project Paving + Detour Updates
Autry crews are continuing work on the East Lyon Station Road crossing, with plans to complete the crossing work by the end of Wednesday, July 8th. Paving is expected to follow on Thursday, July 9th.
Jul 8


Central Avenue Detour Plan
Detour signs will be posted on local streets in the project area and along I-85 to help guide motorists. Drivers are advised to use I-85 Exit 191 to access the Town of Butner during the closure.
Jul 6


East Lyon Station Road & E. Middleton Rd. Travel Advisory June - July
The I-85 Sanitary Sewer Improvement Project is advancing significantly, with heightened construction activities planned for the coming weeks in various high-traffic locations in Butner, NC.
Jun 16


I-85 Sewer Project Two Week Look Ahead: Sewer Installation and Major Traffic Impact Scheduled.
6/15/26 Butner NC: During the next two weeks, I-85 Sanitary Sewer Improvement Project activity will remain active along Joe Peed Road, West Middleton Drive & Lyon Station Rd., West A Street and Central Avenue. Construction crews will: Continue sanitary sewer pipe installation along Joe Peed Road. Continue sewer pipe installation near W. Middleton Drive & E. Lyon Station Road. Continue sewer pipe installation on W. A Street near Central Ave. Set up variable message boards
Jun 15


I-85 SSI Project TWLA : Sewer Installation and Traffic Impacts
Over the next two weeks, I-85 Sanitary Sewer Improvement Project activity will take place along Joe Peed Road, West Middleton Drive, East Lyon Station Road, A Street, and 8th Street. Crews will advance major sewer infrastructure work, including gravity sewer installation, combined force main installation, microtunnel-related work, utility potholing, driveway crossing coordination, and controlled blasting operations.
May 21


Fiscal Year 2026/2027 Budget Adopted
The FY26/27Budget reflects SGWASA’s continued focus on financial stewardship, service reliability, transparency, and organizational readiness. The budget is balanced and supports the Authority’s ability to manage rising operational costs, insurance increases, and major long-term infrastructure needs without additional customer impact.
May 15


I-85 SSI Project - Planned Evening Coating Work in East Middleton Area
Haren Construction is scheduled to perform coating work on wastewater manholes in the East Middleton area tonight and tomorrow night. This work is part of ongoing Construction Package 1 improvements and supports the long-term protection, durability, and performance of wastewater infrastructure serving the area.
May 5


I-85 SSI Project Update: Will Suitt Road Opened
Construction teams reported that the I-85 SSI Project closure near Will Suitt Road has ended, and the road has reopened for normal travel.
May 1


April 27th Will Suitt Road Closure
A closure on Will Suitt Road is scheduled to beginning Monday, April 27, 2026, as Construction Package 2 (CP-2) of the I-85 SSI Project progress. The closure is expected to begin that morning around 7:00 am and remain in place through the posted work period.
Apr 22


Traffic Advisory: Planned Closure at Will Suitt Road and Longwood
South Granville Water and Sewer Authority advises the public that a planned shutdown of Will Suitt Road at Longwood Drive in Creedmoor, NC is scheduled from April 27th through May 1st.
Apr 17


Work Progress Continues West of I-85 with Activity Shifting Toward Will Suitt Road
South Granville Water and Sewer Authority continues to advance major sanitary sewer improvements along the I-85 corridor, with current work moving farther west of the interstate and toward the Will Suitt Road area.
Apr 17


Saturday Work Scheduled at Joe Peed Lift Station Site
Additional construction activity is scheduled for this Saturday, April 11, 2026, at the Joe Peed Lift Station site as crews continue work on the valve and electrical building.
Apr 8


I-85 SSI Project Update
SGWASA’s latest I-85 Sanitary Sewer Improvement Project update highlights continued CP-1 and CP-2 construction activity, including force main installation, utility coordination, traffic management, bypass system work, and ongoing coordination with contractors.
Apr 1


I-85 SSI Project Progress Meeting Review
Active utility installation, structural progress, and coordination efforts supporting the next phase of work continue for the I-85 Sanitary Sewer Improvement Project.
Mar 30