top of page

News


June 3rd East Lyon Station Road Travel Advisory
Pipeline work has progressed to East Lyon Station Road, and the contractor is scheduled to cross East Lyon Station Road from West Middleton Drive on June 3rd.
Jun 2


I-85 SSI Project TWLA : Sewer Installation and Traffic Impacts
Over the next two weeks, I-85 Sanitary Sewer Improvement Project activity will take place along Joe Peed Road, West Middleton Drive, East Lyon Station Road, A Street, and 8th Street. Crews will advance major sewer infrastructure work, including gravity sewer installation, combined force main installation, microtunnel-related work, utility potholing, driveway crossing coordination, and controlled blasting operations.
May 21


Fiscal Year 2026/2027 Budget Adopted
The FY26/27Budget reflects SGWASA’s continued focus on financial stewardship, service reliability, transparency, and organizational readiness. The budget is balanced and supports the Authority’s ability to manage rising operational costs, insurance increases, and major long-term infrastructure needs without additional customer impact.
May 15


I-85 SSI Project - Planned Evening Coating Work in East Middleton Area
Haren Construction is scheduled to perform coating work on wastewater manholes in the East Middleton area tonight and tomorrow night. This work is part of ongoing Construction Package 1 improvements and supports the long-term protection, durability, and performance of wastewater infrastructure serving the area.
May 5


I-85 SSI Project Update: Will Suitt Road Opened
Construction teams reported that the I-85 SSI Project closure near Will Suitt Road has ended, and the road has reopened for normal travel.
May 1


April 27th Will Suitt Road Closure
A closure on Will Suitt Road is scheduled to beginning Monday, April 27, 2026, as Construction Package 2 (CP-2) of the I-85 SSI Project progress. The closure is expected to begin that morning around 7:00 am and remain in place through the posted work period.
Apr 22


Traffic Advisory: Planned Closure at Will Suitt Road and Longwood
South Granville Water and Sewer Authority advises the public that a planned shutdown of Will Suitt Road at Longwood Drive in Creedmoor, NC is scheduled from April 27th through May 1st.
Apr 17


Work Progress Continues West of I-85 with Activity Shifting Toward Will Suitt Road
South Granville Water and Sewer Authority continues to advance major sanitary sewer improvements along the I-85 corridor, with current work moving farther west of the interstate and toward the Will Suitt Road area.
Apr 17


Saturday Work Scheduled at Joe Peed Lift Station Site
Additional construction activity is scheduled for this Saturday, April 11, 2026, at the Joe Peed Lift Station site as crews continue work on the valve and electrical building.
Apr 8


I-85 SSI Project Update
SGWASA’s latest I-85 Sanitary Sewer Improvement Project update highlights continued CP-1 and CP-2 construction activity, including force main installation, utility coordination, traffic management, bypass system work, and ongoing coordination with contractors.
Apr 1


I-85 SSI Project Progress Meeting Review
Active utility installation, structural progress, and coordination efforts supporting the next phase of work continue for the I-85 Sanitary Sewer Improvement Project.
Mar 30


March Board Meeting + Operational Updates
The March Board Meeting video and agenda materials are now available. Park Construction will receive one truckload of pipe today, March 21, on 20th Street. No road closure is expected. Travel with caution in the area.
Mar 20


TWLA
SGWASA’s I-85 Sanitary Sewer Improvement Project is scheduled to continue over the next two weeks with contractor activity focused on East Middleton Drive, West Middleton Drive, Will Suitt Road, West D Street, and the microtunnel receiving pit area.
Mar 18


Road Closure
Crews will continue pump station and pipeline work in the East Middleton area while sewer main installation and site restoration continue on CP-2. Controlled blasting is currently in progress within the work zone, with another session scheduled for 3:00 pm.
Mar 9


I-85 SSI Project Two Week Look Ahead for March 3, 2026
I-85 SSI Project activities will continue progressing over the next two weeks with a focus on controlled blasting, bypass operations, excavation, and continued material deliveries to support pipeline installation. Crews are advancing work in active construction zones while maintaining coordination with project partners and utilities to support safe field conditions, maintain access where possible, and minimize service interruptions.
Mar 3


I-85 SSI Project - 8th Street Detour
Beginning February 23, 2026, the I-85 Sanitary Sewer Improvement (SSI) Project contractor will begin daily blasting activities in the 8th Street construction area. Blasting is anticipated to occur between 7:30 a.m. and 4:30 p.m., and is weather-dependent and subject to Fire Marshal availability.
Feb 23


Weekend Work and Project Progress for the I-85 SSI Project
The I-85 SSI Project has maintained steady progress, and crews will continue moving work forward in the Joe Peed Road and Middleton Drive corridors.
Feb 12


I-85 SSI Project Update: Middleton Drive
This week, JF Wilkerson (Haren Construction Company’s pipeline subcontractor) is expected to begin initial field activities along E. Middleton Drive and W. Middleton Drive, as early as tomorrow.
Feb 9


I-85 SSI CP2 Progress Update
Despite winter conditions, crews continue advancing foundational work, vault and mechanical coordination, and safe excavation activities that support the next phases of construction.
Feb 6


Pre-Blast Surveys
Residents within the I-85 SSI Project construction corridor may receive a Pre-Blast Survey notification letter from Park Construction. This notice is being provided because rock removal may be required as work progresses, and your property may be located within the project’s standard survey radius for potential blasting activities.
Jan 28
bottom of page
