I-85 SSI Project Update: 8th Street Reopening Ahead of Thanksgiving

13 minutes ago
1 min read

BUTNER, NC — SGWASA's I-85 Sanitary Sewer Improvement Project teams are making significant progress toward reopening Butner NC's 8th Street to local traffic ahead of the 2026 Thanksgiving holiday.


Restoring access along this corridor has remained a priority for SGWASA and its contractors, with a focus on minimizing construction-related disruptions for nearby residents and utility customers.


Roadway Restoration Schedule:

  • Monday, November 23: Paving contractor on site preparing for roadway restoration.

  • Tuesday, November 24: Base course asphalt installation scheduled for completion.

  • Wednesday, November 25: Crews will conduct final cleanup between 8:00 am and noon, with the goal of restoring local traffic access ahead of Thanksgiving.

  • Before December 25: Final surface course paving is anticipated, subject to construction conditions and scheduling.


SGWASA appreciates the patience and cooperation of residents throughout construction. This milestone reflects the project team's commitment to advancing essential wastewater infrastructure improvements while reducing impacts on the surrounding community.


Stay Informed: Visit sgwasa.org/i85 to review current project updates, construction schedules, and recordings of project progress meeting sessions.




Posted 11/23/26 by the South Granville Water and Sewer Authority 

Krystle Lee, PIO/Board Secretary/Webmaster