News


October I-85 SSI Progress Meeting
Haren Construction representatives reported completing concrete and rebar installations at both the Joe Peed and East Middleton Lift Stations wet well structures. Specifically, the lower influent channel walls and the lower and upper wet well walls were completed at the Joe Peed Lift Station.
Oct 27


$500,000 Awarded for PFAS Pilot Evaluation and Engineering Design
The State Water Infrastructure Authority has approved SGWASA’s most recent $500,000 funding request, bringing the total project award to $1,000,000 over the past year through the Infrastructure Investment and Jobs Act (IIJA) Drinking Water State Revolving Fund – Emerging Contaminants (DWSRF-EC) program.
Oct 6


Virtual Town Hall
The South Granville Water and Sewer Authority is advancing a critical improvement with the Filter Media Replacement Project. This work...
Sep 24


September I-85 SSI Progress Meeting
SGWASA hosted the fifth monthly progress meeting for the I-85 Sanitary Sewer Improvement (Construction Package 1). The session brought together project partners, contractors, engineers, and agency representatives to review construction progress, safety measures, and scheduling updates.
Sep 19


PFAS Pilot Testing: Protecting Public Health and Preparing for Compliance
SGWASA is committed to meeting new PFAS standards and addressing community concerns. The South Granville Water & Sewer Authority (SGWASA) wants to reassure customers that your drinking water meets all current state and federal safety standards set by the U.S. Environmental Protection Agency (EPA) and the North Carolina Department of Environmental Quality (NCDEQ).
Sep 4


View the August 2025 Board Meeting
Watch the August 12, 2025 SGWASA Board of Directors Meeting. Stay informed on key decisions, infrastructure updates, and ongoing initiatives impacting water and sewer service in southern Granville County.
Aug 13


Update: Filter Media Replacement Project Bid Opening
The South Granville Water and Sewer Authority hosted the scheduled bid opening for the SGWASA Water Treatment Plant Filter Media Replacement Project.
Aug 4


WTP - Filter Media Replacement Project Bid Opening Update
Update: August 13, 2025 In July 2025, at the conclusion of the Water Treatment Plant Filter Media design, Hazen and Sawyer provided a...
Jul 23


Filter Media Replacement Pre-Bid Conference
The South Granville Water and Sewer Authority (SGWASA) announces a Pre-Bid Construction Conference for the WTP Filter Media Replacement Project, scheduled to enter construction in Fall 2025. This vital infrastructure improvement is part of SGWASA’s strategic initiatives to support the southern Granville County community with a reliable and sustainable water treatment system.
Jul 8


I-85 SSI Progress Meeting
During the June 17th, monthly progress meeting, CDM Smith representative Bill Mason led project update conversations with project contractors and SGWASA team members. View meeting discussion topics, minutes, and media files below.
Jun 20


Bid Opening for I-85 Sanitary Sewer Improvement Project – Construction Package 2
As only one bid was received by the submission deadline, and per procurement requirements mandating a minimum of three bids, the team did not proceed with the formal opening.
May 23


Planned Service Notice
In the next phase of the project, the contractor will perform three new waterline connections to the existing mainline along Highway 56.Â
The first tie-in is scheduled for 7:00 AM on Tuesday, May 27, 2025. This portion of the work, indicated in red on the associated map or notice, may result in a temporary drop in water pressure for some customers in the surrounding area.Â
May 23


I-85 SSI Progress Meeting
At the May 20th progress meeting, CDM Smith representative Bill Mason led with team updates and formally introduced Greg Hoch as the new Resident Project Representative (RPR) for Construction Package 1 (CP1) of the I-85 Sanitary Sewer Improvement Project. Jackie Jackson, the initial RPR for CP1, will transition to support Construction Package 2 (CP2) as the RPR once that phase begins.
May 20


Managing Phosphorus for Better Water Quality
SGWASA has worked collaboratively with Enviromix over the past several years to evaluate and improve key water and wastewater treatment technologies. This partnership included a case study at the SGWASA Wastewater Treatment Plant that focused on Enhanced Biological Phosphorus Removal (EBPR). This process has been shown to target phosphorus more efficiently.
May 19


I-85 SSI Project - Controlled Blasting
On Thursday, May 15, Carolina Drilling will return to the Joe Peed Lift Station site to lay out and drill a precision blasting grid. Detonation of this grid is expected to occur in the late afternoon, pending favorable conditions.
May 14


I-85 SSI - Construction Kickoff Recap
On March 28, 2025, the South Granville Water and Sewer Authority hosted the I-85 Sanitary Sewer Improvement Project Construction Celebration
Mar 29


Spring Burnout Notice
IMPORTANT NOTICE TO SGWASA WATER CUSTOMERS Spring 2025 Water System Maintenance Program The South Granville Water and Sewer Authority...
Feb 20


Hydrant Repair
Utility crews are conducting service repairs for fire hydrant on Aiken Avenue in Creedmoor, NC. Customers within the affected service...
Jan 30


System Pressure Advisory
FOR IMMEDIATE RELEASE The following is offered to SGWASA customers as information only. There are no confirmed problems with the drinking...
Jan 28


Winter Repair Information
As winter weather settles in, utility teams generally face heightened challenges, including main breaks and disruptions to critical...
Jan 25