I-85 SSI Progress Meeting
At the May 20th progress meeting, CDM Smith representative Bill Mason led with team updates and formally introduced Greg Hoch as the new Resident Project Representative (RPR) for Construction Package 1 (CP1) of the I-85 Sanitary Sewer Improvement Project. Jackie Jackson, the initial RPR for CP1, will transition to support Construction Package 2 (CP2) as the RPR once that phase begins.
1 day ago


Managing Phosphorus for Better Water Quality
SGWASA has worked collaboratively with Enviromix over the past several years to evaluate and improve key water and wastewater treatment technologies. This partnership included a case study at the SGWASA Wastewater Treatment Plant that focused on Enhanced Biological Phosphorus Removal (EBPR). This process has been shown to target phosphorus more efficiently.
2 days ago


I-85 SSI Project - Controlled Blasting
On Thursday, May 15, Carolina Drilling will return to the Joe Peed Lift Station site to lay out and drill a precision blasting grid. Detonation of this grid is expected to occur in the late afternoon, pending favorable conditions.
May 14


SGWASA News Feature
A recent Triangle Business Journal article highlighted the critical role of water and sewer infrastructure in supporting the natural rate of growth in the Southern Granville County region, featuring the progress underway in southern Granville County. SGWASA is committed to addressing these needs with the SGWASA's I-85 Sanitary Sewer Improvement project.
May 12


Billing - Rollover Balance
Butner, NC - April 22, 2025 - Following SGWASA’s recent billing platform upgrade to the Tyler Technologies utility billing system, some...
Apr 22


I-85 SSI Project CP#2 Bid Announcement
The South Granville Water and Sewer Authority (SGWASA) is accepting bids for the I-85 Sanitary Sewer Improvement Project's Construction...
Apr 15




I-85 SSI - Construction Kickoff Recap
On March 28, 2025, the South Granville Water and Sewer Authority hosted the I-85 Sanitary Sewer Improvement Project Construction Celebration
Mar 29


Consumer Confidence Report
SGWASA routinely conducts rigorous testing of the water provided to our customers. View the Consumer Confidence Report today.
Mar 18


Office Closure - March 17th, 2025
The SGWASA Welcome Center (customer service office) will be closed on March 17, 2025, due to in-service technical training, testing,...
Mar 12


Updated Operational Hours
Butner, NC.  January 10, 2025 —  To ensure the safety of our staff and the ongoing enhancement of our operational capabilities, SGWASA...
Jan 10


SGWASA News Feature
The South Granville Water and Sewer Authority (SGWASA) has taken a major step forward in addressing long-standing sewer capacity issues in the region by awarding contract to Haren Construction for Phase I of the I-85 Sanitary Sewer Improvement Project. This contract, requiring state environmental approval, is part of a larger initiative aimed at improving infrastructure in Granville County.
Jan 2


Winterized Plumbing
Extreme winter weather can impact water infrastructure, such as pipes freezing or breaking.
Dec 2, 2024


October Board Meeting
The South Granville Water & Sewer Authority (SGWASA) Board of Directors will hold its next General Meeting on Tuesday, October 8th, 2024,...
Oct 4, 2024


Fall Burnout Notice
IMPORTANT NOTICE TO SGWASA WATER CUSTOMERS Fall 2024 Water System Maintenance Program The South Granville Water and Sewer Authority...
Oct 1, 2024


SGWASA Site Tours
The South Granville Water & Sewer Authority (SGWASA) recently conducted a site tour to provide stakeholders with a firsthand look at its ope
Sep 30, 2024


Repairs Completed - East Church Street
3:15 PM UPDATE: SGWASA utility crews have successfully completed repairs and are currently working to restore the road to its original...
Sep 24, 2024


Emergency Repair
SGWASA utility crews are responding to report of an emergency repair at 301 West Hillsboro Street in Creedmoor, NC.
Sep 23, 2024


Potential Tropical Cyclone 8
In anticipation of potential flooding, SGWASA utility teams are closely monitoring their systems and taking proactive steps.
Sep 16, 2024


Chemical Tank Replacement Program
SGWASA has successfully completed Phase 2 of the Chemical Tank Replacement Project at the Wastewater Treatment Plant. Â The project...
Sep 13, 2024