HCCI noted that the majority of the work has been clearing the sites and preparing for
construction.
o Clearing at Joe Peed is complete, erosion control measures installed, and they are currently working on the blasting.
o Clearing at East Middleton is complete, erosion control measures installed, and they
are prepping for the undercut of the unsuitable soils.
o After blasting at Joe Peed is complete, they plan to switch the crew over to East Middleton to do the same.
o Wilkerson noted that they have completed the clearing along the pipeline alignments as well.

May 7, 2025 at 12:17:05 AM
Controlled blasting for the I-85 Sewer Project scheduled May 15 at Joe Peed Lift Station—minor vibration expected; weather may impact timing.
___________________ Work continues to advance on the I-85 Sanitary Sewer Improvement Project. Contractors are preparing to complete erosion control installations, including the temporary skimmer basins at both the Joe Peed Pump Station and the East Middleton Pump Station. Drilling and blasting activities remain ongoing at the pump station sites, with temporary power being supplied to support construction activities. Efforts will be concentrated on the layout and development of the East Middleton Pump Station. Meanwhile, subcontractors will continue cleaning work on the existing pipelines throughout the project area.

April 14, 2025 at 8:29:19 AM
Contractors will continue clearing and grubbing activities at the Joe Peed Pump Station site. At the East Middleton Pump Station, plans are underway to complete the installation of erosion control measures, including a temporary skimmer basin.
Subcontractors will also proceed with clearing operations along the pipeline corridors.

April 8, 2025 at 3:19:36 PM
The rain event on April 7, 2025, temporarily halted clearing work by HAREN and KBS. As a result, crews will not be onsite today, April 8, 2025.
KBS, the clearing contractor, plans to work from 7:30 AM to 5:00 PM from Thursday, April 10th to Saturday, April 12th. There will be no work at the E. Middleton site during this period.
HAREN staff will conduct a site visit on Saturday to assess the status of the dewatering pumps.

March 24, 2025 at 2:31:02 AM
General Contractor, Haren Construction, will begin work to clear both E. Middleton and Joe Peed Lift Station Sites.
Subcontractors from JF Wilkerson will be onsite to manage pipeline clearing.
This process (pipeline clearing) will span a longer distance within the shoulder of the road.