All Construction Sites
April 13

Crews will continue laying pipe from the launch pit toward Will Suitt Road. Blasting operations are planned between I-85 and the gas line crossing west of I-85. Final stabilization work, including seed and straw, is scheduled at 8th Street.
Blasting is anticipated once per day west of I-85.
The following traffic impacts are anticipated during this period:
Partial Closures
Will Suitt Road may experience partial closures as heavy equipment is moved through the area. A planned shutdown of Will Suitt Road at Longwood is scheduled for April 27 through May 1.
Open to All Traffic
8th Street and West D Street will remain open to all traffic.
Construction Package 1 Meeting #11
Construction Package 2 Meeting #3