top of page
< Back

All Sites

December 15

Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

- Most construction work for CP1 pause on Thursday and Friday of the next two weeks.

- Plans are in place to continue backfilling the Joe Peed Pump Station. Excavation will continue for valve and electrical services in the building.

- Concrete work is planned for the Joe Peed Pump Station.

- Backfilling will continue at the East Middleton Pump Station.

- Haren plans to continue installation of piping at East Middleton from the station, through the valve vault, and on to the flow meter vault.

- Wilkerson will continue on the influent line at Joe Peed and should begin on the force main work with another crew.


bottom of page