top of page
< Back

Construction Sites

September 19

Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

- Complete Joe Peed Pump Station influent channel walls to elevation 265.50

- Form, rebar, and pour Joe Peed wet well walls to elevation 281.50

- Begin work on Joe Peed influent channel walls to elevation 281.50

- Complete East Middleton Lift Station elevation slab level to 302.00

- Form, rebar, and pour East Middleton walls to elevation level of 313.75

- Begin work on East Middleton top deck

- Leak test lower walls at both stations and backfill to elevations in RFI 22


bottom of page