November 2, 2026

Construction continues across several I-85 SSI Project work areas. Park Construction plans to complete the railroad and microtunnel tie-ins before returning to 8th Street at C Street to finish remaining sewer installation. Work on 8th Street is nearing completion, with final paving tentatively planned before Thanksgiving.
Blasting continues along C Street, where intermittent gas service impacts remain possible. Final paving is also planned for 8th Street and Railroad Avenue.
Along Joe Peed Road, crews will continue 20-inch force-main installation, with traffic flagging and periodic lane closures used as necessary. Next week, installation is planned to continue between WB Clark Road and East Lyon Station.
Traffic Impacts
- 8th Street: Full Closure
- C Street: Full Closure
- Railroad Avenue: Partial Closure
- Joe Peed Road: Periodic lane closures
Please follow posted traffic controls and use caution around active work zones.