All Sites + Central Avenue
July 6, 2026

SGWASA’s I-85 Sanitary Sewer Improvement Project continues to advance across active work areas. Autry crews are continuing work on the East Lyon Station Road crossing, with crossing work expected to be completed by the end of Wednesday, July 8. Paving is expected to follow on Thursday, July 9.
Pipeline installation will continue on Central Avenue with the approved detour in place. Drivers should follow posted detour signage and use I-85 Exit 191 when accessing the Town of Butner. Weekend work is planned in front of the Newton Manufacturing loading docks to help reduce weekday impacts. The Central Avenue closure is currently scheduled from July 6 through August 10.
The blasting schedule remains on hold at this time.
Planned Service Impacts
No service interruptions are anticipated.