All Sites
November 16, 2026

I-85 SSI Project work will continue over the next two weeks with force-main installation, pipe installation, blasting, service connections, paving, and site restoration underway across several active construction areas. Along Joe Peed Road, crews plan to continue installation of the 20-inch force main between WB Clark Road and E. Lyon Station Road before crossing Joe Peed Road near E. Lyon Station Road. A closure and detour of Joe Peed Road between WB Clark Road and E. Lyon Station Road is anticipated Monday through Friday this week. Next week, force-main installation is planned to advance along E. Lyon Station Road toward East Middleton Road, with lane closures used as necessary.
Within CP2, Park Construction plans to continue blasting and pipe installation along C Street. Crews are also installing service connections and completing cleanup along 8th Street, with base-course paving planned before Thanksgiving.
Pipe installation on Railroad Avenue is complete, and crews are cleaning the work area and moving out of this section.
Active Streets & Traffic Impacts
- Joe Peed Road: Closure and detour anticipated between WB Clark Road and E. Lyon Station Road Monday–Friday this week.
- E. Lyon Station Road: Lane closures may be used next week as force-main installation advances toward East Middleton Road.
- C Street: Blasting and pipe installation continue.
- 8th Street: Service installation, cleanup and preparation for base-course paving continue.
- Railroad Avenue: Pipe installation is complete; cleanup and demobilization are underway.
Saturday work has been scheduled for CP2 project teams. Motorists are asked to remain attentive to posted traffic controls and allow additional travel time around active construction areas.
CP1 Project Progress Meeting
CP2 Project Progress Meeting