Construction Sites

August 19

Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

One Month Look Ahead Highlights:

- Form, rebar and pour remaining slab at the Joe Peed LS

- Complete form, rebar, and pour Joe Peed wet well walls

- Form, rebar, and pour Joe Peed lower influent walls
- Finish East Middleton excavation and place crushed stone at base

- Form, rebar, and pour remaining slat at the East Middleton LS

- Begin work on East Middleton wet well walls

- Teams are keeping close watch on submittal times to ensure generator delivery