I-85 SSI Traffic Alert: Multiple Road Closures and Lane Restrictions
Construction is advancing successfully across the I-85 Sanitary Sewer Improvement Project. The following Two Week Look Ahead covers Construction Packages 1 and 2 from August 31st through September 11th, 2026. Under Construction Package 1, JF Wilkerson crews plan to dechlorinate the new 8-inch waterline and collect a bacteriological sample before proceeding with restoration work. Crews will also advance the 20-inch force main leaving Joe Peed. Upcoming work is expected to incl
Sep 2


April 2026 Board Meeting : Proposed FY26/27 Budget Public Hearing
The recent SGWASA Board meeting opened with the administration of the Oath of Office for the Town of Butner Councilperson Tom Lane. The Board welcomed Councilperson Lane back as a returning member of the SGWASA Board, following years of service.
Apr 23


TWLA
SGWASA’s I-85 Sanitary Sewer Improvement Project is scheduled to continue over the next two weeks with contractor activity focused on East Middleton Drive, West Middleton Drive, Will Suitt Road, West D Street, and the microtunnel receiving pit area.
Mar 18


Road Closure
Crews will continue pump station and pipeline work in the East Middleton area while sewer main installation and site restoration continue on CP-2. Controlled blasting is currently in progress within the work zone, with another session scheduled for 3:00 pm.
Mar 9


Pre-Blast Surveys
Residents within the I-85 SSI Project construction corridor may receive a Pre-Blast Survey notification letter from Park Construction. This notice is being provided because rock removal may be required as work progresses, and your property may be located within the project’s standard survey radius for potential blasting activities.