top of page

I-85 SSI Project Update: Middleton Drive

  • Writer: sgwasa
    sgwasa
  • 22 minutes ago
  • 1 min read

This week, JF Wilkerson (Haren Construction Company’s pipeline subcontractor) is expected to begin initial field activities along E. Middleton Drive and W. Middleton Drive, as early as tomorrow.


To support safe and efficient operations, two crews are anticipated to mobilize as follows:


  • Crew 1: Starting at the intersection of West Middleton Dr. and Will Suitt Rd., working east along West Middleton Drive


  • Crew 2: Starting at the East Middleton Lift Station, working west along East Middleton Drive


Work this week will focus on staging materials along the roadway and conducting soft utility digs to locate and verify existing underground utilities. Soft digs are a standard, lower-impact method used to help protect buried infrastructure before excavation begins.




Pipeline installation is planned to begin next week, pending field conditions and progress on utility locating.


Residents should expect active work zones, equipment along the roadside, and periodic lane or shoulder impacts as crews advance. Please use caution, reduce speed near workers, and follow all posted signage and flagging directions.


We appreciate your patience as this work moves forward. If you have questions or need to report a concern in the work area, please contact the Authority through our standard customer service and emergency reporting channels.


 Posted on 2/9/2026 by the South Granville Water and Sewer Authority 

Krystle Lee, PIO/Board Secretary/Webmaster

(919) 575-3367

bottom of page