Butner, NC - I-85 SSI Project construction will continue over the next two weeks with force-main installation, sewer tie-ins, work at 8th and C streets in Butner, NC, blasting, paving, and site restoration underway across multiple active areas.


Along Joe Peed Road, crews will continue installing the 20-inch force main between WB Clark Road and E. Lyon Station Road this week. Traffic will be flagged and periodic lane closures used, as necessary. Crews will also place signs and message boards in preparation for next week’s planned closure and detour.


The section of Joe Peed Road between WB Clark Road and E. Lyon Station Road is planned to close and detour while the crossing is completed. Site restoration and cleanup will also continue.


Within CP2, Park plans to complete the railroad tie-in and reroute services before returning to 8th Street to resume installation at the intersection of 8th and C streets. Following installation, crews will perform testing and service tie-ins. Park will also continue excavating the air gap along C Street for Carolina Drilling, while ASD plans final paving on 8th Street and Railroad Avenue.


Blasting will continue along C Street.


Traffic Impacts

  1. Joe Peed Road: Periodic lane closures this week near WB Clark Road and E. Lyon Station Road; planned closure and detour next week between WB Clark Road and E. Lyon Station Road for the force-main crossing.


  2. 8th Street: Full closure anticipated as installation resumes at 8th and C streets.


  1. C Street: Full closure anticipated as excavation and blasting continue.


  1. Railroad Avenue: Partial closure anticipated during tie-in and paving activities.


Some service impacts are anticipated on 8th Street as installation, testing, and service tie-ins progress. Intermittent gas impacts are possible along C Street as blasting continues.


Motorists are asked to follow posted traffic controls and allow additional travel time around active construction areas.