I-85 SSI Project - Two Week Look Ahead
Butner, NC - I-85 SSI Project work will continue over the next two weeks with sewer installation, railroad and microtunnel tie-ins, pavement restoration, blasting, and site cleanup underway across several active construction areas. Park Construction is completing the railroad tie-in and plans to complete the microtunnel tie-in before returning to 8th Street to resume installation at the intersection of 8th and C streets. The carrier pipe for the jack-and-bore has been threade
Nov 3


Two Week Look Ahead: Closures and Pavement Work
The I-85 SSI Project is moving into the next sequence of field activity as crews transition from Railroad Avenue toward A Street and prepare for upcoming work near 8th and C streets.
Sep 10