I-85 SSI Project - Two Week Look Ahead
Butner, NC - I-85 SSI Project work will continue over the next two weeks with sewer installation, railroad and microtunnel tie-ins, pavement restoration, blasting, and site cleanup underway across several active construction areas. Park Construction is completing the railroad tie-in and plans to complete the microtunnel tie-in before returning to 8th Street to resume installation at the intersection of 8th and C streets. The carrier pipe for the jack-and-bore has been threade
Nov 3


View the October 2026 Board of Directors Meeting
The South Granville Water and Sewer Authority Board of Directors held its regular meeting on Tuesday, October 13, 2026, at Butner Town Hall in Butner, North Carolina.
Oct 24


CP1 & CP2 Project Progress
As the I-85 Sanitary Sewer Improvement Project continues to progress, work remains focused on completing foundation duties for the valve and electrical building and continuing installation of the pressurized sewer piping toward the flow meter vault, with the next phase transitioning into electrical, plumbing, and mechanical work and preparation for the concrete slab.
Jan 28
bottom of page