top of page

News


I-85 SSI Project - Two Week Look Ahead
Butner, NC - I-85 SSI Project work will continue over the next two weeks with sewer installation, railroad and microtunnel tie-ins, pavement restoration, blasting, and site cleanup underway across several active construction areas. Park Construction is completing the railroad tie-in and plans to complete the microtunnel tie-in before returning to 8th Street to resume installation at the intersection of 8th and C streets. The carrier pipe for the jack-and-bore has been threade
4 hours ago
bottom of page
