Joe Peed Road Closure and Pipeline Installation
Access along East Middleton Road will be maintained. Next week, crews will cross Joe Peed Road with the 24” gravity sewer, 8” waterline, and proposed 24” force main. Joe Peed Road will be closed between S. Durham Avenue and WB Clark Road, July 27th through July 30th, with detours in place during closure.
Jul 21


I-85 Sewer Project Two Week Look Ahead: Sewer Installation and Major Traffic Impact Scheduled.
6/15/26 Butner NC: During the next two weeks, I-85 Sanitary Sewer Improvement Project activity will remain active along Joe Peed Road, West Middleton Drive & Lyon Station Rd., West A Street and Central Avenue. Construction crews will: Continue sanitary sewer pipe installation along Joe Peed Road. Continue sewer pipe installation near W. Middleton Drive & E. Lyon Station Road. Continue sewer pipe installation on W. A Street near Central Ave. Set up variable message boards
Jun 15