27 de octubre de 2025, 6:26:44 p.m.

- The Haren Construction team plans to prioritize working on the forming and pouring of the lift station structures.
- Plans are in place to begin forming of the top deck for the Joe Peed Lift Station. Crews will finish pouring the upper wall of the influent channel.
- At the East Middleton Lift Station, the teams will continue working on grinding and patching of the lift station structure.
- Pouring plans are still in progress for the top deck of the East Middleton Lift Station. Once the top deck is poured, Haren will plan to start filling the structure for the water tightness testing.
- Piping will begin outside of the wet well and then a portion of the upstream gravity sewer.
- CDM Smith noted that when Haren pours the top slab they will request a full 3-day break on the concrete testing before pulling the shoring and supports.

19 de septiembre de 2025, 7:08:10 p.m.

- Complete Joe Peed Pump Station influent channel walls to elevation 265.50

- Form, rebar, and pour Joe Peed wet well walls to elevation 281.50

- Begin work on Joe Peed influent channel walls to elevation 281.50

- Complete East Middleton Lift Station elevation slab level to 302.00

- Form, rebar, and pour East Middleton walls to elevation level of 313.75

- Begin work on East Middleton top deck

- Leak test lower walls at both stations and backfill to elevations in RFI 22

19 de agosto de 2025, 6:56:12 p.m.

One Month Look Ahead Highlights:

- Form, rebar and pour remaining slab at the Joe Peed LS

- Complete form, rebar, and pour Joe Peed wet well walls

- Form, rebar, and pour Joe Peed lower influent walls
- Finish East Middleton excavation and place crushed stone at base

- Form, rebar, and pour remaining slat at the East Middleton LS

- Begin work on East Middleton wet well walls

- Teams are keeping close watch on submittal times to ensure generator delivery

16 de julio de 2025, 1:55:41 a.m.

Work is progressing steadily across key areas of the I-85 Sanitary Sewer Improvement Project. Dewatering, excavation, and shoring operations are actively underway and will continue through July 24th at the Joe Peed Lift Station and through August 7th at the East Middleton Lift Station.

Over the next two weeks, construction teams will prioritize yard piping and pipeline installation activities at the East Middleton site to maintain project momentum. Clearing and erosion control measures are scheduled to begin along the Joe Peed Force Main alignment to prepare the area for upcoming phases of construction.

20 de junio de 2025, 3:19:17 p.m.

Haren will continue excavation and shoring at the Joe Peed LS site, aiming to complete or nearly complete work within the next month. At the East Middleton LS, drilling and prep for blasting will continue, with blasting expected to begin within a day or two. Pit boxes will be installed to cover the top 9 feet of the excavation before digging resumes. GSI will alternate drilling operations between the Joe Peed and East Middleton LS sites. Haren emphasized that timely return of rebar, formwork, and concrete mix submittals would help expedite construction. They noted that reviewing only the rebar for the LS sites would be acceptable to speed up the process, and clarified that formwork shop drawings were omitted as they are using pre-engineered forms. Wilkerson stated they plan to begin ordering materials next month following the release of the shop drawings.

22 de mayo de 2025, 1:37:11 p.m.

HCCI noted that the majority of the work has been clearing the sites and preparing for
construction.

o Clearing at Joe Peed is complete, erosion control measures installed, and they are currently working on the blasting.

o Clearing at East Middleton is complete, erosion control measures installed, and they
are prepping for the undercut of the unsuitable soils.

o After blasting at Joe Peed is complete, they plan to switch the crew over to East Middleton to do the same.

o Wilkerson noted that they have completed the clearing along the pipeline alignments as well.

7 de mayo de 2025, 12:17:05 a.m.

Controlled blasting for the I-85 Sewer Project scheduled May 15 at Joe Peed Lift Station—minor vibration expected; weather may impact timing.
___________________ Work continues to advance on the I-85 Sanitary Sewer Improvement Project. Contractors are preparing to complete erosion control installations, including the temporary skimmer basins at both the Joe Peed Pump Station and the East Middleton Pump Station. Drilling and blasting activities remain ongoing at the pump station sites, with temporary power being supplied to support construction activities. Efforts will be concentrated on the layout and development of the East Middleton Pump Station. Meanwhile, subcontractors will continue cleaning work on the existing pipelines throughout the project area.

14 de abril de 2025, 8:29:19 a.m.

Contractors will continue clearing and grubbing activities at the Joe Peed Pump Station site. At the East Middleton Pump Station, plans are underway to complete the installation of erosion control measures, including a temporary skimmer basin.

Subcontractors will also proceed with clearing operations along the pipeline corridors.

8 de abril de 2025, 3:19:36 p.m.

The rain event on April 7, 2025, temporarily halted clearing work by HAREN and KBS. As a result, crews will not be onsite today, April 8, 2025.

KBS, the clearing contractor, plans to work from 7:30 AM to 5:00 PM from Thursday, April 10th to Saturday, April 12th. There will be no work at the E. Middleton site during this period.

HAREN staff will conduct a site visit on Saturday to assess the status of the dewatering pumps.

24 de marzo de 2025, 2:31:02 a.m.

General Contractor, Haren Construction, will begin work to clear both E. Middleton and Joe Peed Lift Station Sites.

Subcontractors from JF Wilkerson will be onsite to manage pipeline clearing.

This process (pipeline clearing) will span a longer distance within the shoulder of the road.