Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

- The Wilkerson team will continue work on the influent line at Joe Peed.
- Crews will begin valve and electrical work at Joe Peed.
- Water testing and backfill operations are planned for the Joe Peed Lift Station.
- Backfilling processes will continue at the East Middleton Lift Station.
- Influent line installation at Joe Peed will proceed, and is scheduled to continue at additional sites by an additional crew to support the Wilkerson team.