I-85 SSI Project
Daily Updates

Next Update:

13 de mayo de 2026

Joe Peed Force Main Work, Launch Pit Pipe Installation, and Sewer Manhole Coating Activity
12 de mayo de 2026

Joe Peed Force Main Work, Launch Pit Pipe Installation, and Sewer Manhole Coating Activity

Today’s project activities include continued pipe installation at the Joe Peed site, force main work along West Middleton Drive, continued installation of 36-inch fiberglass reinforced polymer pipe at the launch pit, sewer manhole coating preparation, and one scheduled controlled blast.

Soldering in progress
11 de mayo de 2026

I-85 SSI Project Weekly Update: Joe Peed Force Main Work and Launch Pit Pipe Installation Advance

Active construction is advancing across the Joe Peed, West Middleton, launch pit, and Will Suitt Road project areas. This week’s activities include continued pipe installation, force main work, 36-inch fiberglass reinforced polymer pipe installation, soil removal, and scheduled controlled blasting.

The I-85 SSI Project remains focused on strengthening wastewater system reliability, improving long-term service capacity, and supporting essential public infrastructure for the South Granville service area. Residents and motorists near active work zones are encouraged to remain alert, follow posted signage, and use caution around crews and equipment.

Joe Peed Force Main Installation and 36-Inch FRP Work at the Launch Pit
8 de mayo de 2026

Joe Peed Force Main Installation and 36-Inch FRP Work at the Launch Pit

Construction work scheduled for today includes continued pipe installation at the Joe Peed site, force main work along West Middleton Drive, installation of 36-inch fiberglass reinforced polymer pipe at the launch pit, soil removal from the Will Suitt Road pipe installation area, and one scheduled controlled blast.

No construction today
7 de mayo de 2026

Rain Adjusted Schedule and Launch Pit Material Delivery

Due to weather conditions, active field work for Construction Package 1 and Construction Package 2 is limited today. Crews will resume scheduled work as conditions allow.

Joe Peed Site Preparation, West Middleton Force Main Work, and West A Street Blasting Activity
6 de mayo de 2026

Joe Peed Site Preparation, West Middleton Force Main Work, and West A Street Blasting Activity

SGWASA is providing this I-85 SSI Project update to keep the community informed of active construction and scheduled field activity. Today’s work includes continued pipe installation, force main work, site preparation at the Joe Peed site, equipment and material staging near the launch pit access road, 36-inch fiberglass reinforced polymer pipe installation, and controlled blasting activity on West A Street near Hanes Geo.

Pipe Installation, East Middleton Coating Work, and West A Street Mobilization
5 de mayo de 2026

Pipe Installation, East Middleton Coating Work, and West A Street Mobilization

CDM Smith provided updates to include planned evening work and developments on upcoming construction site activity. Crews are continuing pipe installation, gravity sewer line work, force main installation, site restoration, equipment staging, and preparation for specialized wastewater coating work at key project locations. These activities support the continued strengthening of wastewater system capacity, reliability, and long-term service for the surrounding area.

Continued Pipe Installation, Lift Station Work, and I-85 Bore Pit Activity
4 de mayo de 2026

Continued Pipe Installation, Lift Station Work, and I-85 Bore Pit Activity

Progress continues across the I-85 SSI Project as crews advance pipe installation, lift station improvements, site restoration, and equipment staging activities. Today’s work includes continued construction activity at the Joe Peed site, East Middleton Lift Station, West Middleton Drive, and the I-85 bore pit area.

Joe Peed, Middleton Drive, and Will Suitt Road Work Continues as Road Reopening Approaches
1 de mayo de 2026

Joe Peed, Middleton Drive, and Will Suitt Road Work Continues as Road Reopening Approaches

Construction activity will continue today across both project areas with ongoing pipe installation, gravity sewer work, landscaping, equipment mobilization, and scheduled blasting operations. In Construction Package 1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In Construction Package 2, crews will shift into site restoration and staging activities along Will Suitt Road and at the launch pit access road. Will Suitt Road is expected to reopen at the close of business today.

30 de abril de 2026

Construction Package 1 and 2 Work Continues with Ongoing Will Suitt Road Activity

Construction activity will continue today across both project areas with ongoing pipeline installation, lift station area work, and scheduled blasting operations. In Construction Package 1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In Construction Package 2, crews will continue installing 36-inch fiberglass reinforced polymer pipe along Will Suitt Road toward Sanitary Manhole 3058, while the current road closure remains in effect through Friday.

Construction Package 1 and 2 Work Continues as Will Suitt Road Restoration Advances
29 de abril de 2026

Construction Package 1 and 2 Work Continues as Will Suitt Road Restoration Advances

Project activity will continue today across both construction areas with pipeline installation, lift station area work, roadway restoration, and scheduled blasting operations. In CP1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In CP2, crews will continue installing 36-inch fiberglass reinforced polymer pipe along Will Suitt Road toward Sanitary Manhole 3058, while paving operations move forward at the road cut. The Will Suitt Road closure will remain in effect through Friday.

Will Suitt Road Installation and Joe Peed Site Support Work Continue
28 de abril de 2026

Will Suitt Road Installation and Joe Peed Site Support Work Continue

Project activity will continue today across both construction areas, with support operations underway at the Joe Peed site and active pipeline installation continuing near Will Suitt Road. East Middleton Drive work will focus on material hauling and site cleanup, while Construction Package 2 crews continue fiberglass reinforced polymer pipe installation and a scheduled controlled blast at the Interstate 85 bore pit. The Will Suitt Road closure will remain in effect through Friday.

Will Suitt Road Closure Begins
27 de abril de 2026

Construction Package 1 and 2 Work Continues as Will Suitt Road Closure Begins

Construction activity will continue across both project areas with active pipeline installation, bore-related work, and a scheduled traffic closure on Will Suitt Road. In Construction Package 1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In Construction Package 2, pipeline installation will advance across Will Suitt Road, one controlled blast is scheduled at the Interstate 85 bore pit, and the Will Suitt Road closure will begin today and remain in place through Friday.

Joe Peed, Middleton Drive, and Interstate 85 Bore Work Continues as Will Suitt Road Closure Remains on Schedule
24 de abril de 2026

Joe Peed, Middleton Drive, and Interstate 85 Bore Work Continues

Construction activity will continue across both project areas with ongoing pipeline installation in CP1 and active bore-related work in CP2. Crews will remain active at the Joe Peed site, along East and West Middleton Drive, and near Will Suitt Road.

One controlled blast is scheduled today at the Interstate 85 bore pit, and the planned closure of Will Suitt Road remains on track to begin Monday, April 27, at 8:30 am.

Joe Peed, Middleton Drive, and Will Suitt Road Work
23 de abril de 2026

Joe Peed, Middleton Drive, and Will Suitt Road Work Progress

Construction activity will continue across both project areas with ongoing pipe installation in CP1 and continued pipeline work near Will Suitt Road in CP2.

Blasting operations are paused for today due to temporary access restrictions associated with railroad track work near 26th Street. Crews remain on schedule for the planned Will Suitt Road closure beginning Monday, April 27th, at 8:30 am.

Joe Peed and Middleton Drive Work Continues as Will Suitt Road Closure Begins April 27
22 de abril de 2026

Joe Peed and Middleton Drive Work Continues as Will Suitt Road Closure Begins April 27

Construction activity will continue across both project areas with ongoing pipe installation, a scheduled controlled blast at the Interstate 85 bore pit, and a planned traffic change on Will Suitt Road. Beginning Monday, April 27, 2026, a full closure on Will Suitt Road is scheduled to support roadway and underground utility work, with follow-up pavement restoration to continue into the next week. Friday, May 1, 2026 completion is dependent upon rock conditions and production progress, repair work.

Joe Peed, Middleton Drive, and Interstate 85 Bore Work Continues
21 de abril de 2026

Joe Peed, Middleton Drive, and Interstate 85 Bore Work Continues

Construction activity will continue across both project areas with ongoing force main and pipeline installation, along with scheduled bore-related work near I-85. In CP1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In CP2, crews will continue pipeline installation toward Will Suitt Road, and one controlled blast is scheduled this afternoon at the I-85 bore pit.

Force Main Installation and Scheduled Blasting Activity
20 de abril de 2026

Ongoing Force Main Installation and Scheduled Blasting Activity

Construction activity will continue in both project areas during this work period. In CP1, crews will remain focused on force main installation at the Joe Peed site and along East and West Middleton Drive. In CP2, pipe installation will continue from the receiving pit toward Will Suitt Road, and two controlled blasts are scheduled at the I-85 bore pit.

17 de abril de 2026

Joe Peed Site, Middleton Drive, and I-85 Bore Activity

Construction activity will continue across both project segments with ongoing pipe installation, bore-related work, and site restoration. In Contract Package 1, crews will remain active at the Joe Peed site and along East and West Middleton Drive. In Contract Package 2, work will continue near the receiving pit toward Will Suitt Road, with a scheduled blast at the Interstate 85 bore pit and restoration efforts at 8th Street and D Street.

Middleton Drive Force Main and Receiving Pit Pipe Installation
15 de abril de 2026

Middleton Drive Force Main and Receiving Pit Pipe Installation

Construction Package 1 remains active with continued pipe installation, force main installation, restoration work, and roadway cleanup, while Construction Package 2 begins new fiberglass reinforced polymer pipe installation from the receiving pit toward Will Suitt Road and includes one scheduled blast at the Interstate 85 bore pit.

Middleton Drive Force Main and Receiving Pit Pipe Installation
14 de abril de 2026

Middleton Drive Force Main and Receiving Pit Pipe Installation

Construction Package 1 remains active with continued pipe installation, force main installation, and driveway restoration work, while Construction Package 2 begins new fiberglass reinforced polymer pipe installation from the receiving pit toward Will Suitt Road and includes one scheduled blast at the Interstate 85 bore pit.

Bore Pit Work
13 de abril de 2026

Middleton Drive Force Main and Receiving Pit Pipe Installation

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along Middleton Drive, while Construction Package 2 begins new fiberglass reinforced polymer pipe installation from the receiving pit toward Will Suitt Road and includes one scheduled blast at the Interstate 85 bore pit.

Middleton Drive Force Main and I-85 Bore Pit Progress
10 de abril de 2026

Middleton Drive Force Main and I-85 Bore Pit Progress

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 advances finish grading, equipment mobilization, and scheduled blasting at the Interstate 85 bore pit.

Middleton Drive Force Main and I-85 Bore Pit Blasting
9 de abril de 2026

Middleton Drive Force Main and I-85 Bore Pit Blasting

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 advances finish grade work, site restoration, equipment mobilization, and scheduled blasting activities near the Interstate 85 bore pit.

Bore Pit Blasting
8 de abril de 2026

Middleton Drive Force Main and I-85 Bore Pit Blasting

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 continues fiberglass reinforced polymer pipe installation along Eighth Street and begins scheduled blasting activity at the Interstate 85 bore pit.

Drill Equipment Upstream
7 de abril de 2026

Middleton Drive Force Main and Eighth Street Installation

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 continues fiberglass reinforced polymer pipe installation along Eighth Street and advances drill setup activities ahead of planned drilling and blasting operations between Interstate 85 and Railroad Avenue.

FRP Installation
6 de abril de 2026

Middleton Drive Force Main and Eighth Street FRP Installation

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 continues fiberglass reinforced polymer pipe installation along Eighth Street and prepares for drilling and blasting operations between Interstate 85 and Railroad Avenue.

Bypass Pump Work
2 de abril de 2026

Middleton Drive Force Main and Spoil Removal Activities

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 is focused on spoil removal and bypass system removal activities.

No work will take place on Construction Package 1 or Construction Package 2 tomorrow, in observance of the Good Friday holiday.

Middleton Force
1 de abril de 2026

Middleton Drive Force Main and Manhole Invert Work

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 is focused on manhole concrete work and bypass system removal, with no additional blasting planned this week.

Middleton Drive
31 de marzo de 2026

Middleton Drive Force Main and Eighth Street Installation

Construction Package 1 remains active with pipe installation, force main installation, and utility locating activities, while Construction Package 2 continues FRP pipe installation along Eighth Street with no additional blasting planned for the rest of the week.

Force Main and Eighth Street Installation Team
30 de marzo de 2026

Middleton Drive Force Main and Eighth Street Installation

Construction Package 1 remains active with continued pipe installation at the Joe Peed site and resumed force main installation along Middleton Drive, while Construction Package 2 continues pipe installation across Eighth Street with manhole setting activities and scheduled blasting at West D Street and the microtunnel site.

Paused pipe installation
27 de marzo de 2026

Joe Peed Pipe Installation and Eighth Street Progress

Construction Package 1 remains active with continued pipe installation and site restoration activity, while Construction Package 2 continues pipe installation across Eighth Street with one scheduled blast at the microtunnel site.

I-85 SSI
26 de marzo de 2026

East Middleton Force Main and Eighth Street Pipe Installation

Pipe installation remains active in Construction Package 1, while Construction Package 2 continues with fiberglass reinforced polymer pipe installation, scheduled microtunnel blasting, and roadway restoration work along D Street.

Blasting and construction continue
25 de marzo de 2026

Joe Peed Pipe Installation and D Street Progress

Construction activity remains active in both phases of the I-85 Sanitary Sewer Improvement Project, with continued pipe installation in Construction Package 1 and ongoing pipe installation and scheduled blasting at the microtunnel site in Construction Package 2.

Pipe and Blasting
24 de marzo de 2026

East Middleton Force Main and CP-2 Blasting Operations

Pipe installation and force main work remain active in CP-1, while CP-2 crews continue FRP installation and scheduled blasting at the microtunnel site and West D Street.

Microtunnel
23 de marzo de 2026

Force Main Work Continues as CP-2 Blasting Proceeds

Construction activity remains active across both phases of the I-85 Sanitary Sewer Improvement Project, with continued pipe and force main installation in CP-1 and ongoing FRP installation and scheduled blasting operations in CP-2.

Pipe Installation and Blasting
20 de marzo de 2026

Joe Peed Pipe Installation and Revised CP-2 Blasting Schedule

CP-1 pipe and force main installation activities remain underway, while CP-2 work continues with FRP installation and a revised blasting schedule that now includes one 12:00 pm microtunnel pit blast and one 11:00 am D Street hand shot.

i-85 SSI
18 de marzo de 2026

Force Main and FRP Installation Continue as Blasting Operations Advance CP-2 Work

Construction activity remains active across both phases of the I-85 Sanitary Sewer Improvement Project, with ongoing force main and FRP pipe installation alongside scheduled blasting operations in CP-2.

I85 SSI
17 de marzo de 2026

FRP Installation and Microtunnel Mobilization Continue

Force main installation is resuming at key CP-1 locations while CP-2 work continues with FRP pipe installation and microtunnel drilling mobilization.

Rain Date
16 de marzo de 2026

Construction Pause

CP-1 crews are securing materials and preparing for weather conditions ahead of upcoming installation work, while no CP-2 contractor activity is scheduled for today.

East Middleton Force Main and FRP Sewer Main
13 de marzo de 2026

East Middleton Force Main and FRP Sewer Main Work

CP-1 crews are advancing valve vault preparation and force main installation along East Middleton Drive and West Middleton Drive, while CP-2 crews continue FRP sewer main installation, backfilling, and manhole invert grouting with no blasting scheduled today.

Blasting Continues
12 de marzo de 2026

East Middleton Force Main and CP-2 Outfall Blasting

CP-1 crews are preparing for rain while force main installation continues along East Middleton Drive, and CP-2 crews will continue FRP sewer main installation, structure grouting, manhole vacuum testing, and scheduled outfall blasting at 10:00 am.

Blasting
11 de marzo de 2026

East Middleton Force Main Work and CP-2 Outfall Blasting

CP-1 crews continue backfill, cleanup, conduit installation, and force main work along East Middleton Drive, while CP-2 crews advance FRP sewer main installation and backfilling as scheduled, with Carolina Drilling set to blast rock in the outfall at 10:00 am and 1:00 pm outside the roadway work restriction area.

Forced Main
10 de marzo de 2026

Main Installation and Rock Blasting

CP-1 crews are advancing lift station piping and force main installation and testing, while CP-2 crews continue FRP sewer main work, site restoration, ground-speed testing, and scheduled outfall rock blasting outside the Enbridge stop-work area.

Forced Main
9 de marzo de 2026

East Middleton Force Main Work and CP-2 Blasting

Crews will continue force main installation in the East Middleton area, along with ongoing pump station work, conduit installation, erosion control maintenance, sewer main installation, and site restoration in CP-2.

Controlled blasting in CP-2 is scheduled for 11:00 am. and 3:00 pm.

JF Wilkerson
6 de marzo de 2026

Lift Station Piping, Force Main Installation, and CP-2 FRP Work

Crews are advancing lift station construction with through-slab process piping and continuing force main installation along the East Middleton corridor. CP-2 teams are installing FRP sewer mains and restoring disturbed areas, while Carolina Drilling remains on standby pending resolution of Enbridge Gas coordination items.

I-85 SSI Project Work
5 de marzo de 2026

East Middleton Force Main and CP-2 FRP Work

CP-1 crews are continuing pump station backfilling and force main installation along East Middleton Drive, including work near the Middleton Lift Station driveway and between Stardust Lane and West Middleton Drive. CP-2 crews are continuing FRP sewer main installation, while Carolina Drilling is temporarily paused pending resolution of an Enbridge Gas coordination issue.

RPR Updates
4 de marzo de 2026

Force Main and FRP Installations

CP#1 crews will continue pump station backfilling, hauling fill to support East Middleton work, and advancing roofing and force main installation near the East Middleton Lift Station and Stardust Lane. CP#2 crews will continue installing FRP sewer main segments, while drilling remains paused pending resolution of an Enbridge Gas coordination issue.

Visit the I-85 SSI Project Page For Details