January 7

Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

* Material deliveries are planned to continue, ductile iron pipe has been delivered, on site.
* The first 20 manholes, rings and covers, services, and saddles will arrive over the next two weeks.
* PVC pipe and coupling deliveries are anticipated delivery within approximately one month.
* Park has released structures up to 11th Street in Butner, NC.
* Travel with caution on C, D, and 8th Streets as crews will be present assisting with traffic direction.
* The East Middleton Lift Station will include liquid-phase odor control work, consisting of layout and excavation for the concrete equipment pad and placement of the specified stone base.


logotipo de sgwasa

Autoridad de agua y alcantarillado del sur de Granville

415 Avenida Central, Suite B

Butner, Carolina del Norte 27509

​

​

TELÉFONO

(919) 575-3367

​

​

FAX

​

​

(919) 575-4547

Archivo

Financiero

Contacto del personal

nuevos clientes

Clientes existentes

© Derechos de autor
bottom of page