December 15

- Most construction work for CP1 pause on Thursday and Friday of the next two weeks.
- Plans are in place to continue backfilling the Joe Peed Pump Station. Excavation will continue for valve and electrical services in the building.
- Concrete work is planned for the Joe Peed Pump Station.
- Backfilling will continue at the East Middleton Pump Station.
- Haren plans to continue installation of piping at East Middleton from the station, through the valve vault, and on to the flow meter vault.
- Wilkerson will continue on the influent line at Joe Peed and should begin on the force main work with another crew.