top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

7/10/26, 11:51 a.m.

A temporary detour is planned for WB Clark Road during next week's road crossing, while full closures are anticipated on 8th Street, C Street, and A Street as applicable to active construction.

Contract Package 1 (CP1)
This week, crews will excavate and haul away contaminated soil near the old Joe Peed lift station. Upon completion, gravity sewer installation will continue, along with installation of the 20-inch force main.
Haren Construction plans to complete the WB Clark Road crossing Monday through Wednesday, OCT 12th – 14th. A temporary detour will be in place on WB Clark Road while the crossing work is underway. Traffic flagging and lane closures will continue on Joe Peed Road as necessary to support construction.

Contract Package 2 (CP2)
Park Construction plans to continue pipe installation along A Street to complete the railroad tie-in, following completion of jack and bore operations; and transition to 8th Street, following the railroad tie-in. Crews will also continue digging the air gap along C Street for Carolina Drilling.

Spiders will be used for the microtunnel work and to complete bore-and-jack tunneling operations. Final paving on Laundry Avenue and Railroad Avenue is scheduled to be completed by next week, with blasting is planned along C Street.

Ver lista de alertas

Please be advised that blasting and construction activities may cause noise near the project area. Other work may begin as early as 7:00 AM and end at 10:00 PM, while jack-and-bore tunneling near the Norfolk Southern railroad crossing will continue 24 hours a day until complete. Nearby customers may hear tunneling noise overnight. Deliveries, blasting and excavation may also affect traffic on multiple streets within the construction area.

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page