Proyecto SSI I-85
La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.
Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.
Actualizaciones de construcción:
20/11/26, 1:50 p.m.
I-85 SSI Project work will continue over the next two weeks with force-main installation, pipe installation, blasting, service connections, paving, and site restoration underway across several active construction areas. Along Joe Peed Road, crews plan to continue installation of the 20-inch force main between WB Clark Road and E. Lyon Station Road before crossing Joe Peed Road near E. Lyon Station Road. A closure and detour of Joe Peed Road between WB Clark Road and E. Lyon Station Road is anticipated Monday through Friday this week. Next week, force-main installation is planned to advance along E. Lyon Station Road toward East Middleton Road, with lane closures used as necessary.
Within CP2, Park Construction plans to continue blasting and pipe installation along C Street. Crews are also installing service connections and completing cleanup along 8th Street, with base-course paving planned before Thanksgiving.
Pipe installation on Railroad Avenue is complete, and crews are cleaning the work area and moving out of this section.
Active Streets & Traffic Impacts
- Joe Peed Road: Closure and detour anticipated between WB Clark Road and E. Lyon Station Road Monday–Friday this week.
- E. Lyon Station Road: Lane closures may be used next week as force-main installation advances toward East Middleton Road.
- C Street: Blasting and pipe installation continue.
- 8th Street: Service installation, cleanup and preparation for base-course paving continue.
- Railroad Avenue: Pipe installation is complete; cleanup and demobilization are underway.
Saturday work has been scheduled for CP2 project teams. Motorists are asked to remain attentive to posted traffic controls and allow additional travel time around active construction areas.
Ver lista de alertas
Please be advised that blasting and construction activities may cause noise near the project area. Other work may begin as early as 7:00 AM and end at 10:00 PM, while jack-and-bore tunneling near the Norfolk Southern railroad crossing will continue 24 hours a day until complete. Nearby customers may hear tunneling noise overnight. Deliveries, blasting and excavation may also affect traffic on multiple streets within the construction area.

I-85 SSI Project Progress Meetings
SOCIOS DEL PROYECTO
Socios financieros:
Departamento de Calidad Ambiental de Carolina del Norte
Departamento de Agricultura de los Estados Unidos
Socios comunitarios miembros de SGWASA:
Ciudad de Stem
Ciudad de Butner
Ciudad de Creedmoor
Condado de Granville