top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

6/2/26, 5:44 a.m.

Recent snow caused only minor delays. Park plans to use the A Street staging area. Teams addressed concerns surrounding the pre-blast survey activity.

NCDOT coordination is ongoing, including follow-up on closure restrictions. CDM Smith provided a draft approach to apply the value engineering credit through adjusted unit prices on payment applications, which Park is reviewing.

Near-term work includes continued material deliveries (pipe and manholes in place up to 11th Street within LODs), erosion control completion, access road finalization on both sides of Interstate 85, and finishing the microtunnel pad area; remaining pipe deliveries are estimated at four to six weeks out, and PVC pipe/couplings are estimated at two to four weeks out.

Bypass prep is anticipated the week of 2/16 or 2/23, with bypass pipe and pumps to be delivered and assembly to begin. Park will submit a vibration control plan for the Newton area, has notified blasters, is coordinating the Armorock manhole submittal, and is awaiting the microtunnel submittal being prepared by Finch Engineering. CCTV of residential areas is planned to begin the week of February 9th.

Traffic control will be used for deliveries with minimal short-term impacts (including C Street), no service impacts are expected at this time, and impacts may begin in two to three weeks.

Please be advised that noise disruptions may occur during the clearing and excavation activities. Clearing may begin as early as 7:00 AM.

Ver lista de alertas

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page