top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

5/5/26, 6:26 p.m.

Over the next two weeks, crews will continue gravity sewer work, force main installation, utility potholing, site grading, wastewater manhole coating, microtunnel access preparation, pipe installation, and controlled blasting activities. This work remains focused on strengthening wastewater system reliability, improving long-term service capacity, and supporting essential public infrastructure in the South Granville service area.

Construction Package 1 work will continue in the East Middleton, West Middleton, and Joe Peed areas, including gravity sewer work at the East Middleton Lift Station, force main installation along West Middleton Drive, and upcoming 20-inch force main work at the Joe Peed site.

Construction Package 2 work will continue near Will Suitt Road, the microtunnel access road, the launching pit, the railroad crossing area, 8th Street, and A Street. Park Construction is expected to complete relocation from Will Suitt Road to the microtunnel access road and begin installing pipe from the launching pit toward the railroad.

Carolina Drilling is expected to continue controlled blasting from the launching pit toward the railroad crossing before shifting toward A Street, including West A Street.

Please be advised that noise disruptions may occur during the blasting and construction activities. Work may begin as early as 7:00 AM. Traffic impacts should be expected on multiple streets within the construction area, primarily associated with deliveries, blasting activity, and excavation operations with work ending at 10:00 PM.

Ver lista de alertas

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page