top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

29/7/26, 1:14 p.m.

I-85 SSI Project construction, over the next two weeks, will focus on continued pipeline installation along Joe Peed Road, Laundry Avenue, Railroad Avenue, and Central Avenue, while crews advance multiple critical phases of the I-85 Sanitary Sewer Improvement Project. Work includes completion of the Joe Peed utility crossings, continued pavement restoration along A Street and Central Avenue, and the start of micro tunneling operations. Blasting activities remain on hold pending completion of gas utility coordination.

Motorists may experience temporary traffic impacts along Joe Peed Road, Laundry Avenue, Railroad Avenue, A Street, Central Avenue, West Middleton Drive, East Middleton Drive, and E. Lyon Station Road. Joe Peed Road will remain closed through Thursday between U.S. Highway 15 and W.B. Clark Road while crews complete multiple utility crossings and permanent pavement restoration. Joe Peed Road between W.B. Clark Road and E. Lyon Station Road will remain open throughout the week. The Central Avenue closure and signed detour remain in place as construction progresses, with drivers encouraged to use I-85 Exit 191 when traveling to and from the Town of Butner.

Ver lista de alertas

Please be advised that noise disruptions may occur during the blasting and construction activities. Work may begin as early as 7:00 AM. Traffic impacts should be expected on multiple streets within the construction area, primarily associated with deliveries, blasting activity, and excavation operations with work ending at 10:00 PM.

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page