
Proyecto SSI I-85
La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.
Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.
Actualizaciones de construcción:
20/10/26, 4:58 p.m.
WB Clark Road Update: JF Wilkerson has begun the delayed force-main road crossing. The work is being managed with a single-lane closure rather than a full road closure, and completion is anticipated by the end of this week. Traffic flagging and lane closures will also continue along Joe Peed Road as necessary.
Additional work includes continued installation toward 8th Street, the railroad tie-in, C Street excavation and blasting, microtunnel work at the Norfolk Southern Railroad crossing, and final paving on Laundry Avenue and Railroad Avenue.
Next week, 20-inch force-main work is planned near E. Lyon Station and East Middleton, with installation also continuing between WB Clark Road and E. Lyon Station.
Ver lista de alertas
Please be advised that blasting and construction activities may cause noise near the project area. Other work may begin as early as 7:00 AM and end at 10:00 PM, while jack-and-bore tunneling near the Norfolk Southern railroad crossing will continue 24 hours a day until complete. Nearby customers may hear tunneling noise overnight. Deliveries, blasting and excavation may also affect traffic on multiple streets within the construction area.

I-85 SSI Project Progress Meetings
SOCIOS DEL PROYECTO
Socios financieros:
Departamento de Calidad Ambiental de Carolina del Norte
Departamento de Agricultura de los Estados Unidos
Socios comunitarios miembros de SGWASA:
Ciudad de Stem
Ciudad de Butner
Ciudad de Creedmoor
Condado de Granville




































