top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

19/3/26, 12:29 p.m.

For CP1, Crew 1 will continue potholing existing utilities as needed and installing the 16-inch force main from the East Middleton Lift Station toward East Lyon Station Road. Crew 2 will continue 24-inch gravity sewer installation on March 16 and March 17 before temporarily moving offsite for emergency work, with next week’s Crew 2 activities still to be determined. Traffic impacts may include flagging operations on East Middleton Drive, driveway crossing coordination with property owners, and lane closures on Will Suitt Road and West Middleton Drive as needed for equipment access, pipe installation, and material deliveries. Planned service impacts remain limited to driveway crossings along East Middleton Drive.

For CP2, crews will continue material deliveries, install pipe across West D Street, stabilize the ground after trench backfilling, remove the bypass pipe, and complete pre-blast surveys around the microtunnel receiving pit. Carolina Drilling is scheduled to move into the receiving pit area at I-85, and blasting is anticipated at the microtunnel receiving pit, while blasting on 8th Street remains on hold until further notice. Short-term traffic control will be used during deliveries and construction activity near 8th Street, D Street, and Will Suitt Road. Sewer service impacts are expected to be minimal during pipeline installation, gas service impacts from blasting are expected to remain minimal this week, and while water service impacts are possible during blasting, repair materials are on site for rapid response.

Please be advised that noise disruptions may occur during the blasting and construction activities. Work may begin as early as 7:00 AM. Traffic impacts should be expected on multiple streets within the construction area, primarily associated with deliveries, blasting activity, and excavation operations.

Ver lista de alertas

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page