top of page
Construction Site

Proyecto SSI I-85

La Autoridad de Agua y Alcantarillado de South Granville se asoció con los expertos en ingeniería CDM Smith para llevar a cabo el Proyecto de Mejora del Alcantarillado Sanitario I-85.

Este proyecto reemplazará materiales obsoletos para mantener una infraestructura que satisfaga las demandas de capacidad presentes y futuras del condado de Granville.

Construction Tape.png

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Gerente de construcción
Jackie Jackson

Representante residente del proyecto CDM Smith

Ingeniero de proyectos
Michael Sloop

Gerente de Proyecto CDM Smith

Director Ejecutivo Scott N. Schroyer

Líder del proyecto SGWASA

Descargar Un mes por delante

Actualizaciones de construcción:

3/8/26, 8:05 p.m.

This week, crews plan to complete the 8-inch waterline, restore the gravity sewer right-of-way, install the 24-inch valve near Will Suitt Road, and continue restoration along West Middleton Drive. Next week, work will include grading along the gravity sewer alignment on Joe Peed Road and beginning installation of the 20-inch force main from the Joe Peed Pump Station. Flagging will be used as needed along Joe Peed Road, East Lyon Station Road, West Middleton Drive, and East Middleton Drive. A lane closure is planned on Joe Peed Road during force-main installation. No utility service impacts are anticipated.

Park Construction crews will continue pipe installation along Railroad Avenue, while Young Construction begins advancing the microtunnel casing, with progress dependent on rock conditions. Blasting remains on hold. Full road closures are anticipated on Laundry Avenue and Railroad Avenue near active construction areas. No utility service impacts are anticipated.

Site cleanup and maintenance activities are planned for 8th Street, in Butner, NC.

Ver lista de alertas

Please be advised that noise disruptions may occur during the blasting and construction activities. Work may begin as early as 7:00 AM. Traffic impacts should be expected on multiple streets within the construction area, primarily associated with deliveries, blasting activity, and excavation operations with work ending at 10:00 PM.

I-85 SSI Project Progress Meetings

I-85 SSI Project Progress Meetings

SOCIOS DEL PROYECTO

Socios financieros:

Departamento de Calidad Ambiental de Carolina del Norte

Departamento de Agricultura de los Estados Unidos

 

Socios comunitarios miembros de SGWASA:

Ciudad de Stem

Ciudad de Butner

Ciudad de Creedmoor

Condado de Granville

Aún no hay ninguna entrada publicada en este idioma
Una vez que se publiquen entradas, las verás aquí.

Actualizaciones de noticias

bottom of page