Please be advised that blasting and construction activities may cause noise near the project area. Other work may begin as early as 7:00 AM and end at 10:00 PM, while jack-and-bore tunneling near the Norfolk Southern railroad crossing will continue 24 hours a day until complete. Nearby customers may hear tunneling noise overnight. Deliveries, blasting and excavation may also affect traffic on multiple streets within the construction area.

The next work sequence shifts attention toward A Street, 8th Street, C Street, and continued trenchless construction preparation.

Park Construction is moving to A Street to continue pipe installation from Mount Hope toward B Street. Crews plan to move to 8th Street by the middle of next week.

C Street is expected to close beginning September 15, 2026, based on the anticipated construction sequence. NCDOT inspection has been requested for September 14. Both 8th Street and C Street are expected to be closed for blasting and pipe-laying operations.

Park is also planning limited Saturday work (9/12) for pre-vacuum testing of manholes and shoulder cleanup following recent paving.

The Norfolk Southern Railroad bore pit excavation has begun. Replacement cutters for the I-85 microtunnel are expected to arrive this week, with boring operations to resume after installation.

Joe Peed Road work remains active, with gravity sewer and 20-inch force main activities continuing. Motorists should expect flagging and lane closures as needed near the work area.

Anticipated Traffic Impacts: 8th Street and C Street closures; traffic controls near Joe Peed Road; Railroad Avenue paving activity.