top of page
Construction Workers Measuring

I-85 SSI Project

The South Granville Water & Sewer Authority partnered with engineering experts CDM Smith to conduct the I-85 Sanitary Sewer Improvement Project.

 

This project will replace aging materials to maintain an infrastructure that meets Granville County’s present and forthcoming capacity demands.

Construction Tape.png

DAILY PROJECT UPDATE

View daily field plan information for SGWASA’s I-85 Sanitary Sewer Improvement Project, received from Resident Project Representatives.

Next Update:

April 6, 2026

April 2, 2026

Middleton Drive Force Main and Spoil Removal Activities

CP-1
Haren crews are continuing pipe installation at the Joe Peed site.

JFW crews will continue 16-inch force main installation along Middleton Drive.

Autry crews are installing 24-inch force main along West Middleton Drive.

CP-2
Park crews are continuing to load out spoil from the site. Crews will also begin stripping bypass pumps and removing associated piping.

Carolina Drilling crews will not conduct blasting for the remainder of the week.

Construction Package 1 remains active with continued pipe and force main installation at Joe Peed and along the Middleton corridor, while Construction Package 2 is focused on spoil removal and bypass system removal activities.

No work will take place on Construction Package 1 or Construction Package 2 tomorrow, in observance of the Good Friday holiday.


TWLA Updates:

4/1/26, 8:30 PM

As SGWASA continues tracking progress on the I-85 Sanitary Sewer Improvement Project, the latest progress meeting reflected continued construction activity across both CP-1 and CP-2.

In CP-1, crews are expected to remain focused on force main installation and utility coordination along East Middleton Drive and West Middleton Drive, with traffic control and driveway coordination continuing to support safe construction access and localized resident movement.

Service impacts are expected to remain limited, and no Haren or JF Wilkerson work is planned for Good Friday, April 3, 2026. In CP-2, the project team reported recent progress on bypass installation, pipe and manhole placement, blasting activity, and microtunnel coordination, while also noting that upcoming work will depend heavily on coordination with Enbridge Gas. Planned efforts include continued utility installation, pipe testing, bypass removal, and additional blasting activity near the receiving pit as the team works to maintain forward momentum.

News Updates

bottom of page