
I-85 SSI Project
The South Granville Water & Sewer Authority partnered with engineering experts CDM Smith to conduct the I-85 Sanitary Sewer Improvement Project.
This project will replace aging materials to maintain an infrastructure that meets Granville County’s present and forthcoming capacity demands.
DAILY PROJECT UPDATE
View daily field plan information for SGWASA’s I-85 Sanitary Sewer Improvement Project, received from Resident Project Representatives.
Next Update:
November 9, 2026
November 6, 2026
Rock Removal Supports Railroad Avenue Pipeline Connection Work
CP-1 Updates
Haren maintains construction activity at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is progressing with sewer line installation, while Autry is installing the sewer force main.
CP-2 Updates
Park Construction is working to connect the Norfolk Southern Railroad bore pipe to the previously installed pipeline along Railroad Avenue. Crews are also hammering through rock encountered during this portion of the installation.
No controlled blasting is scheduled today on C Street.

Rock removal remains part of today's I-85 SSI construction activity as Park Construction works to connect the Norfolk Southern Railroad bore pipe to the previously installed pipeline along Railroad Avenue. Crews are continuing to break through rock to accommodate the connection, while CP-1 operations remain active at the Joe Peed lift station and along Joe Peed Road. No blasting is scheduled today on C Street.
TWLA Updates:
11/4/26, 12:21 PM
Construction continues across several I-85 SSI Project work areas. Park Construction plans to complete the railroad and microtunnel tie-ins before returning to 8th Street at C Street to finish remaining sewer installation. Work on 8th Street is nearing completion, with final paving tentatively planned before Thanksgiving.
Blasting continues along C Street, where intermittent gas service impacts remain possible. Final paving is also planned for 8th Street and Railroad Avenue.
Along Joe Peed Road, crews will continue 20-inch force-main installation, with traffic flagging and periodic lane closures used as necessary. Next week, installation is planned to continue between WB Clark Road and East Lyon Station.
Traffic Impacts
- 8th Street: Full Closure
- C Street: Full Closure
- Railroad Avenue: Partial Closure
- Joe Peed Road: Periodic lane closures
Please follow posted traffic controls and use caution around active work zones.












