36-Inch Fiberglass-Reinforced Pipe Installation Advances to Central Avenue Road Cut
July 2, 2026
CP-1 Updates
Haren staff continue pipe installation at the Joe Peed site. JF Wilkerson crews continue sewer line installation along Joe Peed Road, today. Autry staff will continue force main installation at the East Lyon Station Road crossing.
CP-2 Updates
Park Construction has completed installation of the 36-inch fiberglass-reinforced pipe (FRP) on A Street up to the Central Avenue road cut. Staff are continuing to haul spoil from the A Street excavation site.
Teams are installing temporary fencing and a 20-foot gated entrance at the receiving pit access road off Will Suitt Road to secure equipment associated with upcoming microtunneling activities.
Park staff are planning to secure and shut down the site at noon, today, in observance of the holiday