Central Avenue Crossing Work Continues on A Street

July 9, 2026

CP-1 Updates
Haren staff are continuing pipe installation at the Joe Peed site. JF Wilkerson staff are continuing sewer line installation along Joe Peed Road. Autry staff are continuing force main work at the East Lyon Station Road crossing.

CP-2 Updates
Park staff are continuing installation of the 36-inch fiberglass-reinforced pipe (FRP) on A Street as work advances across Central Avenue.