8th Street Pipe Work Advances with One Controlled Blast Scheduled
October 20, 2026
CP-1 Updates
Haren remains active at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is progressing sewer line installation, while Autry is advancing sewer force main work.
CP-2 Updates
Park is moving pipe installation forward on 8th Street. Carolina Drilling is scheduled to conduct one controlled blast today at 1:00 PM.