A Street Pipe Laying Moves Ahead with 8th Street Blasting Scheduled

September 15, 2026

CP-1 Updates
Haren is working at the Joe Peed lift station.

Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park is moving forward with pipe laying activities on A Street, and is also addressing air gap and heave removal on 8th Street. Young Construction is advancing I-85 microtunnel boring.

A second Young Construction crew is performing Norfolk Southern Railroad boring activities. Carolina Drilling is scheduled to conduct two controlled blasts today on 8th Street at 11:00 AM and 3:00 PM.