8th Street Blasting and A Street Pipe Laying Remain Active
September 16, 2026
CP-1 Updates
Haren is working at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.
CP-2 Updates
Park is advancing pipe laying activities on A Street, and is also addressing air gap work and heave removal on 8th Street. Young Construction is progressing I-85 microtunnel boring. A second crew is performing Norfolk Southern Railroad boring activities.
Carolina Drilling is scheduled to conduct two controlled blasts today on 8th Street at 11:00 AM and 3:00 PM.