Railroad Avenue Installation Moves Forward as Microtunnel Operations Progress

August 6, 2026

CP-1 Updates
Haren is progressing work at the Joe Peed lift station. JF Wilkerson is installing sewer line along Joe Peed Road. Autry is performing force main work near Lyon Station Road.

CP-2 Updates
Park crews are placing 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction is advancing microtunnel operations.

SGWASA appreciates the community’s patience and attention near active construction areas as this wastewater infrastructure work moves forward.