top of page
Weather Holds Blasting While Underground Work Progresses
September 24, 2026
CP-1 Updates
Haren is progressing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry advances sewer force main construction.
CP-2 Updates
Park is carrying pipe installation forward on A Street. Young Construction is advancing I-85 microtunnel boring, while a second crew continues Norfolk Southern Railroad bore activities.
Carolina Drilling will not conduct blasting today due to weather conditions.

bottom of page
