Weather Holds Blasting While Underground Work Progresses

September 24, 2026

CP-1 Updates
Haren is progressing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry advances sewer force main construction.

CP-2 Updates
Park is carrying pipe installation forward on A Street. Young Construction is advancing I-85 microtunnel boring, while a second crew continues Norfolk Southern Railroad bore activities.

Carolina Drilling will not conduct blasting today due to weather conditions.