Blasting Paused Through the Weekend as Underground Work Continues
September 25, 2026
CP-1 Updates
Haren is progressing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is continuing sewer line installation while Autry advances sewer force main construction.
CP-2 Updates
Park is continuing pipe installation on A Street. Young Construction is advancing I-85 microtunnel boring, while a second Young crew continues Norfolk Southern Railroad bore activities.
Carolina Drilling will not conduct blasting today. Blasting activities are scheduled to resume Monday.