Site Preparation and Material Removal Lead Today’s I-85 SSI Work

October 2, 2026

CP-1 Updates
Haren is maintaining progress at the Joe Peed lift station.

Along Joe Peed Road, JF Wilkerson continues sewer line installation while Autry advances sewer force main construction.

CP-2 Updates
Park will not install pipe today. Crews are instead hauling excavated material from A Street and C Street and preparing the work areas for expected rainfall. Activities include securing material stockpiles and completing erosion and sediment control inspections and maintenance.

Young Construction continues dismantling the tunnel boring machine (TBM) and wash plant as this phase of the tunneling operation progresses; and will also continue Norfolk Southern Railroad bore activities.

No controlled blasting is scheduled for today.