Railroad Avenue Pipeline Connections and Microtunnel Backfill Work Progress
November 4, 2026
CP-1 Updates
Haren is carrying out construction activities at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is advancing sewer line installation, while Autry is installing the sewer force main.
CP-2 Updates
Park Construction is working to connect the Norfolk Southern Railroad bore pipe with the previously installed pipeline along Railroad Avenue.
Blasting is scheduled for 1:00 PM today on C Street.
Young Construction is progressing through equipment dismantling and backfilling the microtunnel excavation.
SGWASA appreciates the community’s cooperation as crews complete pipeline connections and address remaining excavation areas. Motorists are encouraged to follow posted traffic guidance and remain attentive near active construction zones.