A Street Excavation Begins as 8th Street Test Blasts Are Scheduled

September 3, 2026

CP-1 Updates
Haren is advancing work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson is installing sewer line while Autry performs sewer force main work.

CP-2 Updates
Park is continuing to mobilize materials and equipment to A Street, with excavation expected to begin today. Young Construction has a limited crew onsite to service equipment and maintain field readiness.

Carolina Drilling is scheduled to conduct test blasts today on 8th Street at 11:00 AM and 3:00 PM.