Rain Conditions Shift Construction Work to Site Cleanup and Preparation
July 24, 2026
CP-1 Updates
Haren continues work inside the Joe Peed lift station.
JF Wilkerson and Autry are currently waiting out rain. Sewer line work along Joe Peed Road and force main work may resume this afternoon if site conditions allow.
CP-2 Updates
Park crews are cleaning the site following recent rainfall and conducting erosion and sediment control inspections across the project area.
Young Construction continues preparing for upcoming microtunnel work by pumping water from the launch pit excavation.