Railroad Avenue Pipe Installation and Joe Peed Lift Station Work Continue
July 31, 2026
CP-1 Updates
Haren continues work at the Joe Peed lift station. JF Wilkerson's work on sewer line installation along Joe Peed Road is on schedule. Autry will proceed with force main work near Lyon Station Road.
CP-2 Updates
Park crews are progressing with the installation of the 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction continues launch pit work off Will Suitt Road.