8th Street Pipe Installation Begins as Paving and Bore Preparation Continue

October 12, 2026

CP-1 Updates
Haren continues work at the Joe Peed lift station. Along Joe Peed Road, JF Wilkerson continues sewer line installation, while Autry continues sewer force main construction.

CP-2 Updates
Park will continue cleanup on A Street and begin pipe installation on 8th Street. ASD will be onsite conducting asphalt overlay work on Laundry Avenue, Railroad Avenue, and 19th Street.

Young Construction will continue preparation for pipe-pushing activities at the Norfolk Southern Railroad bore and microtunnel sites.

Carolina Drilling is scheduled to conduct one controlled blast on C Street at 1:00 PM.