top of page
Microtunnel Drilling Begins as Railroad Avenue Pipe Installation Continues
August 3, 2026
CP-1 Updates
Haren continues work at the Joe Peed lift station, with JF Wilkerson progressing sewer line installation along Joe Peed Road. Autry crew are making great strides with force main work near Lyon Station Road.
CP-2 Updates
Park crews continue installation of the 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction plans include beginning micro tunnel drilling.

bottom of page
