Microtunnel Drilling Begins as Railroad Avenue Pipe Installation Continues

August 3, 2026

CP-1 Updates
Haren continues work at the Joe Peed lift station, with JF Wilkerson progressing sewer line installation along Joe Peed Road. Autry crew are making great strides with force main work near Lyon Station Road.

CP-2 Updates
Park crews continue installation of the 36-inch fiberglass-reinforced pipe (FRP) on Railroad Avenue. Young Construction plans include beginning micro tunnel drilling.