A Street Pipe Installation Continues with Weekend Cleanup Scheduled

July 10, 2026

CP-1 Updates
Haren continues pipe installation at the Joe Peed site. JF Wilkerson teams proceed with sewer line installation along Joe Peed Road, today. Autry has plans for ongoing force main work at the East Lyon Station Road crossing.

CP-2 Updates
Park crews are continuing installation of the 36-inch fiberglass-reinforced pipe (FRP) on A Street as work advances across Central Avenue.

Weekend Work Schedule
Park will not perform pipe installation over the weekend. A four-person crew will be onsite Saturday to clean portions of A Street where pipe installation has occurred, move construction materials, and service equipment.