Pipe Installation Continues on Laundry Avenue
July 21, 2026
CP-1 Updates
Haren continues pipe installation at the Joe Peed site. JF Wilkerson continues sewer line installation along Joe Peed Road. Autry continues force main work near East Lyon Station Road.
CP-2 Updates
Park crews continue installation of the 36-inch fiberglass-reinforced pipe (FRP) on Laundry Avenue.
Young Construction continues bore pit work off Will Suitt Road.