Railroad Avenue Installation and Microtunnel Work Remain Active

August 20, 2026

CP-1 Updates
Haren continues forward progress on the Joe Peed lift station, advancing key structural and mechanical components.

Along Joe Peed Road, JF Wilkerson is actively installing new sewer line infrastructure, while Autry crews continue work on the sewer force main system, extending pressurized conveyance capacity through the corridor.

CP-2 Updates
Park crews are steadily placing 36-inch fiberglass-reinforced pipe (FRP) along Railroad Avenue, building out a durable and corrosion-resistant wastewater conveyance line.

Young Construction is progressing with microtunnel operations, carefully advancing underground pipe installation with minimal surface disruption.