I-85 SSI Project Weekly Update: Joe Peed Force Main Work and Launch Pit Pipe Installation Advance

May 11, 2026

Construction Package 1 work will continue in the Joe Peed and West Middleton project areas. Haren Construction crews will continue pipe installation at the Joe Peed site. JF Wilkerson crews have resumed force main installation at the Joe Peed site, marking continued progress on wastewater infrastructure improvements in that area. Autry crews will continue force main work along West Middleton Drive.

Construction Package 2 work will continue at the launch pit and near the Will Suitt Road pipe installation area. Park Construction crews have resumed installation of the 36-inch fiberglass reinforced polymer pipe at the launch pit and will continue loading out soil from the Will Suitt Road pipe installation area to support ongoing construction activity.