May 2 - May 22
Joe Peed Pump Station
Scheduled work that involves loud noise from drilling and blasting procedures will begin Tuesday, May 7th, at the Joe Peed and East Middleton Lift Stations. Additional drilling and blasting work is planned for the East Middleton Lift Station on Wednesday, May 14th.

Controlled blasting for the I-85 Sewer Project scheduled May 15 at Joe Peed Lift Station—minor vibration expected; weather may impact timing.
___________________ Work continues to advance on the I-85 Sanitary Sewer Improvement Project. Contractors are preparing to complete erosion control installations, including the temporary skimmer basins at both the Joe Peed Pump Station and the East Middleton Pump Station. Drilling and blasting activities remain ongoing at the pump station sites, with temporary power being supplied to support construction activities. Efforts will be concentrated on the layout and development of the East Middleton Pump Station. Meanwhile, subcontractors will continue cleaning work on the existing pipelines throughout the project area.