SGWASA Engineering Project
WTP Water Valve Replacement
Design is 100% complete, with an estimated construction cost of $710,000. The project remains on hold pending public bidding in 2026 and updates to the Capital Improvement Plan.
Budget:
Design and evaluation: $155,980; estimated construction: $710,000
Current Milestone:
Capital Improvement Plan, Project 101-10.
This project addresses recurring valve failures and leaks while improving bypass capability and system redundancy at the water treatment plant.
Design was 100% complete. Construction remained on hold pending public bidding and coordination with the updated Capital Improvement Plan.
Funding:

Hazen & Sawyer
Recurring leaks and valve failures along the water main between the clearwell and finished-water pumps at SGWASA’s Water Treatment Plant highlighted erosion concerns and the need for improved bypass capability and system redundancy.
Hazen and Sawyer completed the evaluation of repair alternatives and preparation of design, permitting, and bidding documents. Evaluation and design costs totaled $155,980, with an estimated construction cost of $710,000.
As of October 2026, design was 100% complete. Construction remained on hold pending coordination with the updated Capital Improvement Plan, with public bidding planned for 2026.
Learn More
This section provides supporting documents and media related to the project. The resources below consolidate key information on the project and closely connected topics that inform planning, compliance, and coordination.
Project Support & Resources
Use the engineering quick links to easily navigate to project information, contact the project team, and view project archives.