Update treatment plant asset inventories and assess critical infrastructure to guide long term maintenance and improvement planning.

Budget:

$150K grant + $30K match

Current Milestone:

$150,000 NCDEQ grant plus a $30,000 SGWASA match

Infrastructure inspections and asset evaluations remained underway, with completion scheduled for March 2027.

Grant accepted and task order approved; project commenced December 2025 and is scheduled for completion by January 2027.

Funding:

SGWASA Water Treatment Master Plan

McGill Associates

SGWASA applied for and received a $150K grant from the NCDEQ for this project. SGWASA is working with McGill Associates on this project. This project is just in its initial stages of working through all the required grant paperwork submittals and authorization. SGWASA will add the required 20% funding match of $30K for this project.
In summary, the South Granville Water and Sewer Authority intends to conduct an Asset Inventory and Assessment study of the Authority’s water treatment plant in a project described as the Water Plant Master Plan. This project will build upon previous water system AIA work and will include tasks such as an update of asset inventories, condition assessment of critical assets, and other components of an asset management plan.

Learn More

This section provides supporting documents and media related to the project. The resources below consolidate key information on the project and closely connected topics that inform planning, compliance, and coordination.


Project Support & Resources

​

Use the engineering quick links to easily navigate to project information, contact the project team, and view project archives. 

bottom of page